CLIENT
Vault Minerals
VALUE
$2.1 million
CONTRACT TYPE
Schedule of Rates
START DATE
Oct 2024
DURATION
3 months
LOCATION
160 km east of
Geraldton, WA
SCOPE
Construction of Stage 2 Lift in Cell A – Scope of works included:
- 48,000m2 of Foundation Prep.
- 86,600m3 of embankment lift using reclaimed Tailings Material from within the TSF for the
perimeter and dividing wall. - 20,300m3 of mine waste L&H to construct downstream embankment and decant.
- Raise existing decant tower.
ACHIEVEMENTS
- Zero LTIs.
- Works completed on time and on budget.