Granny Smith Cell 3G

CLIENT
Gold Fields

VALUE
$4.6 million

CONTRACT TYPE
Schedule of Rates

START DATE
May 2024

DURATION
5 months

LOCATION
25 km south of Laverton,
WA

SCOPE

Construction of Upstream Lift to Cell 3 – Scope of works included:

  • 117,000m2 of Foundation Prep.
  • 190,000m3 of embankment lift using reclaimed Tailings Material from with Cell 3
  • 125,000m3 of mine waste L&H to construct downstream embankment and decant.
  • Raise existing decant tower.

ACHIEVEMENTS

  • Zero LTIs.
  • Additional works awarded:
    • Repair works to Cell 1 & 2 Running Track
    • Cell 2 Decant Raise