CLIENT
Silver Lake Resources Pty
Ltd
VALUE
$2.06 million
CONTRACT TYPE
Schedule of Rates
START DATE
April 2023
DURATION
3 months
LOCATION
160 km east of
Geraldton, WA
SCOPE
Construction of Stage 2 Lift in Cell B – Scope of works included:
- 22,000m2 of Foundation Prep.
- 93,700m3 of embankment lift using reclaimed Tailings Material from within the TSF for the
perimeter and dividing wall. - 19,100m3 of mine waste L&H to construct downstream embankment and decant.
- Raise existing decant tower.
ACHIEVEMENTS
- Zero LTIs.
- Additional works awarded:
- Rehab worksto Gullewa Mine Site TSF 1
- Deflector Mine Waste Dump Topsoil Rehab works
- Extension worksto Deflector Core yard.
