CLIENT
Gold Fields
VALUE
$4.6 million
CONTRACT TYPE
Schedule of Rates
START DATE
May 2024
DURATION
5 months
LOCATION
25 km south of Laverton,
WA
SCOPE
Construction of Upstream Lift to Cell 3 – Scope of works included:
- 117,000m2 of Foundation Prep.
- 190,000m3 of embankment lift using reclaimed Tailings Material from with Cell 3
- 125,000m3 of mine waste L&H to construct downstream embankment and decant.
- Raise existing decant tower.
ACHIEVEMENTS
- Zero LTIs.
- Additional works awarded:
- Repair works to Cell 1 & 2 Running Track
- Cell 2 Decant Raise