Civil Earthworks | Mine Site Rehabilitation | Civil Contracting

Mt Monger TSF1 Stage 1 & Rehabilitation

CLIENT
Vault Minerals

VALUE
$2.9 million

CONTRACT TYPE
Schedule of Rates

START DATE
January 2025

DURATION
5 months + ongoing

LOCATION
75 km southeasto

SCOPE
Construction of Stage 1 Lift to TSF1 & rehabilitation of TSF 1 & TSF 2 – Scope of works included:

  • 32,000m2 of Foundation Prep.
  • 78,000m3 of embankment lift using reclaimed Tailings Material from TSF 1 for the Final 3m
    lift.
  • 45,000m3 of mine waste L&H to construct downstream embankment and decant.
  • Raise existing decant tower.
  • Construct 2 additional Return Water Ponds
  • Rehabilitation works to TSF 1 and TSF Batters with topsoil.