CLIENT
Vault Minerals
VALUE
$2.9 million
CONTRACT TYPE
Schedule of Rates
START DATE
January 2025
DURATION
5 months + ongoing
LOCATION
75 km southeasto
SCOPE
Construction of Stage 1 Lift to TSF1 & rehabilitation of TSF 1 & TSF 2 – Scope of works included:
- 32,000m2 of Foundation Prep.
- 78,000m3 of embankment lift using reclaimed Tailings Material from TSF 1 for the Final 3m
lift. - 45,000m3 of mine waste L&H to construct downstream embankment and decant.
- Raise existing decant tower.
- Construct 2 additional Return Water Ponds
- Rehabilitation works to TSF 1 and TSF Batters with topsoil.