Bellevue Gold MineInfrastructure – Bulk Earthworks

CLIENTS
GRES
Bellevue

VALUE
$2 million
$6 million – ongoing

CONTRACT TYPE
Schedule of Rates

START DATE
Sep 2022
Aug 2022

DURATION
6 months
10 months + ongoing

LOCATION
42 km North of Leinster, WA

SCOPE
Scope of Works for GRES

  • 90,576m2 of Clear & Grub to Plant Site.
  • 50,300m3 of Bulk Earthworks to Construct Process Plant Pads.
  • 25,500m3 of Bulk Earthworks to Construct Raw, Event & Process Water Ponds.

Scope of Works for Bellevue Direct

  • 309,480m2 of Clearing and topsoil removal to access roads and Power station Pads
  • 180,000m3 of Bulk Earthworks to Access Roads, Power Pads and Carparks
  • 800m of 600mm Dia Culverts Install
  • Drainage works

ACHIEVEMENTS
Awarded additional Works.

  • Westralia Pit Berm Extension Valued at $500,000