Deflector MineTSF2 Cell B Stage 2

CLIENT
Silver Lake Resources Pty Ltd

VALUE
$2.06 million

CONTRACT TYPE
Schedule of Rates

START DATE
April 2023

DURATION
3 months

LOCATION
160 km east of Geraldton, WA

SCOPE
Construction of Stage 2 Lift in Cell B – Scope of works included:

  • 22,000m2 of Foundation Prep.
  • 93,700m3 of embankment lift using reclaimed Tailings Material from within the TSF for the perimeter and dividing wall.
  • 19,100m3 of mine waste L&H to construct downstream embankment and decant.
  • Raise existing decant tower.

ACHIEVEMENTS

  • Zero LTIs.
  • Additional works awarded:
    – Rehab works to Gullewa Mine Site TSF 1
    – Deflector Mine Waste Dump Topsoil Rehab works
    – Extension works to Deflector Core yard.